Friday February 29th ~ Ade arrived out to the property early to broom off the first and second floors for the work the crew was doing with setting the ridge and valley beams as well as the fireplace framing. The picture of Ade brooming off the subfloor is what will be in our soon to be Great Room. The other picture is looking from the Kitchen into the Dining Room.
Sunday, March 2, 2008
Saturday, February 23, 2008
Second Floor Lumber Delivery
Some Views from the First Floor Interior




The following photos were taken from the first floor in which the individual rooms are now framed in. The top photo is a view looking through one of our dining room windows, over to the french doors that will open off of the great room onto the deck.
The second photo was taken out of a window in the Master Bedroom.
The third is the view looking out of the french doors off of the Master Bedroom onto the deck.
The fourth photo is the view standing from the great room with your back to the window wall. The stairwell is in the middle both going down into the basement and up to the second floor. To the right is the dining room and the eat in kitchen. To the left is the Master bedroom, bathroom and walk-in closet.
It is so nice to see the sun out again in these photos!
Second Floor Joists and Floor On!


The external structure is coming along nicely. Our building crew has made some great progress this month with the log stacking. As of Friday, the second floor joists, rim board and plywood floor sheathing have been installed. They are hopeful that by the end of next week (2/29), the crane/boom arm truck will be out to help set the ridge and valley glulam beams (Douglas Fir) for the roof.
Saturday, February 2, 2008
Rough View of Interior Framing
First Floor Stacked Logs Nearing Completion



Aside from the front window wall which needs the logs notched a certain way, most of the other walls have reached their 18 course stack heighth (this does not include the 3 courses of siding that will reside beneath course one to cover up the rim board and the deck/porch flashing). Here are some pictures after the snow we received on Friday 2-1-08.
Friday, January 18, 2008
First Floor Taking Shape

The building crew has been back for a week now and we're really starting to see progress with the first floor structure.
Corey in the corner of what will be the formal Dining Room
Ade across the subfloor in the Master Bedroom/Walk-in Closet and Bathroom
The 2 Kitchen windows
Side of the Home facing some woods and the Wolf Lake Road(window opening is in Formal Dining Room) and the kitchen is to the right of the Dining Room