Monday, May 26, 2008

Spring at the Forbes Homestead






Here are some miscellaneous photos taken around the property. Trees and shrubs are greening up, wildflowers are starting to bloom and weeds are growing in full force. We also seem to have some skeletal remains of what looks to be a deer that we found near the back of the property. Cody found it quite interesting.


Saturday, May 10, 2008

House Updates





Here are some photos taken today with the updates on the house. All of the shingles are on but those covering the shed dormer (the shingles can't go on until the 3 skylights arrive with the window order and are installed). The ridge vent still needs to be installed also. The second floor framing is just about complete, so we can see the loft, 3 bedrooms and bathroom taking shape. Also, you can start to see flashing being strategically placed around the house for supply and return air vents by our HVAC sub-contractor, Aspen Heating and Cooling of Jackson. I also took a "Spring" photo looking out of our Great Room windows (the last one I took had some snow on the ground and the trees were still bare) . The windows and doors order will be arriving on-site this upcoming Friday (5/16), so stay posted for more updated shots.


Garage Siding



















The garage "half log" siding is coming along. We ordered Northern White Cedar siding for the garage from our log home company so that it would look the same as the full logs used for the house. I help out with a lot of the cutting and measuring of the siding while Ade and his Dad nail the siding up. The gable portion of the garage is kind of tricky for cutting siding as it needs to be mitered, so this portion is pretty much left up to Ade and his Dad. It also gets tricky when working around windows and doors as well. We have completed one side and the back as of tonight. We hope to have another side done sometime this week and then get started on the front of the garage.

Tuesday, April 29, 2008

Giant PEX Puzzle Maze






On Tuesday and Wednesday April 22nd and 23rd, we worked on creating the giant barrier PEX maze that will allow hot water to flow through it and help insulate/heat the basement ("Hydronic Heat"). We screwed more than 500 pex clips into the rigid foam board to secure the 1000 feet of 1/2" oxygen barrier PEX tubing in place. In most places, the tubing is 12" on center, except for where it is closer to the outside window and door walls, where we tried to loop it 9" or less on center due to higher heat loss potential. The basement is divided into 4 different "runs", but it is considered all one "zone". There are 2 copper manifolds, each with 4 ports which allow for output of the hot water and return of the water post heating of the slab. We needed to pressurize the system to check for leaks before the inspection (and during the concrete pour). No Leaks! The system stayed pressurized at 50 psi (which was the inspection requirement) and we successfully passed our 2nd plumbing inspection on Thursday April 24th. The 4" thick poured basement will encapsulate all of this tubing, so everything needed to be perfect before pouring. Once the basement is poured, it is difficult to change or fix anything. After we are in the house, we plan to hook the system up to its own heat source, most likely a tankless hot water heater.

Foam Board Installation




On Monday and Tuesday, April 21st and 22nd, we began the task (under the assumption that our basement was being poured on Friday April 25th . . . this had since been moved to Tuesday, April 29th due to potential rain) of leveling the earth floor in the basement to prepare for the radiant floor underlayment. Ade went through a process of using a large landscape rake, 2X4 and a level to even out all areas of the basement based on the level of the house and jackpost footings. After the leveling was complete, we covered the floor with a 6 mil visqueen vapor barrier, and started piecing together (like a giant 1300 square foot puzzle) the 2" thick "Foamular" foam board to cover the entire area (except over the top of the 6 jackpost footings). The so called "extruded polystyrene" foam boards themselves will lend an R-10 value to the floor.

Sub Slab Plumbing












Ade and His Dad were able to complete the "sub slab" (translated into "below the basement floor") plumbing on Saturday and Sunday April 19th and 20th. Our Plumbing (and Mechanical) inspector for Grass Lake popped out Monday evening to inspect and we successfully passed our first plumbing inspection. Mom and Dad Chauvin and I were busy bees during this process, cleaning up all of the building junk that has been scattered around the house and on the property since December (not to mention all of the scap and other crap collecting inside of the house shell).

Wednesday, April 16, 2008

Pre-Sierra Leone Updates










We took some pictures the day before we left on our mission trip to Sierra Leone, but ran out of time to upload them to the blog. All of these shots are from Friday, March 28th. More to come now that we are back . . .